1. Support Portal
  2. Off-Grid Solar Systems

Commodore Off-Grid System Shutdown Procedure

1. Turn off the “MAIN SWITCH STANDALONE SUPPLY ” circuit breaker located in “AC Switchboard”

 

2. Turn off the “MAIN SWITCH PV INVERTER SUPPLY ” circuit breaker located in “AC Switchboard”-if present

 

3. Turn off the “MAIN SWITCH GENERATOR SUPPLY” circuit breaker located in “AC Switchboard” and disable generator auto start at generator control panel –if present

 

4. Turn off all “PV ARRAY D.C ISOLATORS” located in “DC Switchboard” and below PV Inverter-if present

 

5. Turn off all “MPPT BATTERY DC ISOLATOR’S”– located In “DC Switchboard“

 

6. Turn off all Victron Inverter switches (located on Victron Inverters)

 

7. Turn off all “BATTERY SYSTEM D.C ISOLATOR’S”

 

8. Turn off all Battery Switches if present (in battery cabinet)

 

9. Start up Procedure is the reverse of the Shutdown Procedure